§ 54-18-201. Public utility to obtain approval for high voltage power lines.


Latest version.
  • (1) Except as provided in Subsections (2) and (3), a public utility shall comply with the requirements of this chapter before beginning construction or operation of:
    (a) a high voltage power line; or
    (b) an upgraded high voltage power line.
    (2) A public utility is not subject to the provisions of this chapter if the public utility has on or before May 12, 2009:
    (a) filed an application for or obtained a certificate of convenience and necessity for a high voltage power line in accordance with the provisions of Section 54-4-25; or
    (b) has initiated the acquisition of right-of-way for the construction of the high voltage transmission line.
    (3) A transmission line that is subject to federal permitting is not subject to the provisions of this chapter.