UTAH CODE (Last Updated: January 16, 2015) |
Title 54. Public Utilities |
Chapter 18. Siting of High Voltage Power Line Act |
Part 2. Public Utility Duties for High Voltage Power Lines |
§ 54-18-201. Public utility to obtain approval for high voltage power lines.
Latest version.
-
(1) Except as provided in Subsections (2) and (3), a public utility shall comply with the requirements of this chapter before beginning construction or operation of: (a) a high voltage power line; or (b) an upgraded high voltage power line. (2) A public utility is not subject to the provisions of this chapter if the public utility has on or before May 12, 2009: (a) filed an application for or obtained a certificate of convenience and necessity for a high voltage power line in accordance with the provisions of Section 54-4-25; or (b) has initiated the acquisition of right-of-way for the construction of the high voltage transmission line. (3) A transmission line that is subject to federal permitting is not subject to the provisions of this chapter.
Enacted by Chapter 316, 2009 General Session