§ 17-36-55. Fees collected for construction approval. (Effective 5/13/2014)


Latest version.
  • (1) As used in this section, "construction project" is as defined in Section 38-1a-102.
    (2) If a county collects a fee for the inspection of a construction project, the county shall ensure that the construction project receives a prompt inspection.
    (3) If a county cannot provide a building inspection within three business days, the county shall promptly engage an independent inspector with fees collected from the applicant.
Enacted by Chapter 197, 2014 General Session