§ 73-28-402. Agreement for delivery -- Period for repayment of costs.
Latest version.
-
(1) The board and each district shall establish by contract the timing and amount of developed water to be delivered to the district. (3) If a contract was made after the project's completion date, the district shall repay the preconstruction and construction costs within a period not to exceed 50 years from the date that the contract was made. (4) The board shall establish and charge a reasonable interest rate for the unpaid balance of reimbursable preconstruction and construction costs.
Enacted by Chapter 216, 2006 General Session