§ 73-5a-205. Approvals void after one year if construction delayed -- Exceptions.


Latest version.
  • (1) Any approval granted under Section 73-5a-203 is void one year after the date of approval if construction has not started.
    (2) The state engineer may extend the approval in one year increments:
    (a) upon a showing of reasonable cause for delay; and
    (b) provided state-of-the-art design criteria has not changed in the intervening period.
Enacted by Chapter 319, 1990 General Session